McClellan-Kerr Arkansas River Navigation System
     U.S. Army Corps of Engineers
     Little Rock District
     ------------------------------------------------------------------------------
     Long Range Forecast for the Entrance Channel
           Date: 02-Dec-22
     Forecasted 7 a.m. Stages, Elevations and Mean Daily Flows
     (NWS forecast assumes two days additional precipitation)
     ------------------------------------------------------------------------------
     Date       Helena  Ark City    MPLD      MPLD     L01   Clarendon Differential
                 Stage    Stage   H/W ELEV  T/W ELEV  Elev     Flow
                 (ft)     (ft)      (ft)      (ft)    (ft)     (cfs)      (ft)
     ------------------------------------------------------------------------------
     Dec  2 *     0.6      2.0     117.8     112.2    118.8    11,000     1.0
          3 *     0.9      1.7     118.2     111.8    119.1    11,000     0.9
          4 *     1.9      1.8     117.8     112.1    118.8    12,000     1.0
          5 *     2.8      2.6     118.2     113.0    119.1    12,000     0.9
          6 *     3.7      3.5     117.8     113.8    118.8    12,000     1.0
          7 *     4.5      4.3     118.2     114.6    119.1    12,000     0.9
          8 L     5.2      5.1     115.5     115.3    116.9    13,000     1.4
          9       5.9      5.8     116.1     115.9    117.4    13,000     1.3
         10       6.3      6.4     116.7     116.5    118.0    13,000     1.3
         11       5.7      6.8     117.0     116.8    118.3    13,000     1.3
         12       4.9      6.2     116.4     116.2    117.8    13,000     1.4
         13 R     4.1      5.4     118.2     115.5    119.1    12,000     0.9
         14 *     3.4      4.6     117.8     114.8    118.8    12,000     1.0
         15 *     2.8      4.0     118.2     114.2    119.1    12,000     0.9
         16 *     2.1      3.3     117.8     113.6    118.8    12,000     1.0














             MPLD crest gates are raised as t/w recedes to elev 115.
             MPLD crest gates are lowered as t/w rises above elev 115.

         R   Date crest gates raised.
         *   Crest gates in raised position with lock in operation.
         L   Date crest gates lowered.